PeopleOS as an assisted operating model

Every step below runs from week one on a thin data spine + AI concierge + the tools Equals Five already owns. Software is bought when a volume trigger fires, and built only when a gate proves the join is used. Dates are real; each gate names its owner, entry criteria, exit criteria and the choice being made.

Read this with: the 3 Jun build-vs-buy analysis (buy the commodity, build the join) and the 29 Jul brief review (80–85% off-the-shelf). This page is the "how", in operating detail.

0 · The frame — three tracks, five gates

Track 1 — Operate (from W1): run the full PeopleOS process assisted — humans + AI concierge on an Airtable spine. Track 2 — Buy (from W6): adopt commodity tools only when measured volume fires a trigger. Track 3 — Build (from W13): Tim builds only the joins the assisted quarter proved. Gates G0–G4 sit between the tracks; nothing crosses without passing its gate.

1 · Solution map — who owns what

James / Leadership

  • G0 scope decision: internal vs KubiqAI product
  • Approves Core/Flex/Network categorisations
  • Stage-2 interviews + Meeting-3 onboarding
  • Monthly metrics review · gate sign-offs

Anthony · solution design

  • Owns the operating model + this map
  • Field-cut workshop · spine schema (W1)
  • Defines gates, tolerances, prompts
  • Gates Tim's estimates & backlog (G4)
  • Weekly ops review chair (Fri)

AI concierge

  • ScoreApp export → assessment draft (24h)
  • NL talent search over spine + CV corpus
  • Interview question packs from gaps
  • Huddle voice-memo → summary → spine
  • Invoice ↔ LoE ↔ time three-way check
  • Never decides — drafts + flags only

Recruitment lead (Josh)

  • Vacancy briefs · publishes JD
  • Human review gate on every AI assessment
  • Stage-1 interviews · onboarding meetings 1–2
  • Spine data owner — completeness ≥95%

Tim (Tiaan) · architect

  • W1 guardrails call — architecture principles
  • Observes assisted quarter · logs build candidates
  • G4: receives proven backlog, estimates against it
  • Builds the join (Nov+) — not the platform

Finance

  • Weekly approved-time ledger
  • Month-end reconciliation (AI-checked)
  • Owns exceptions — every one named + resolved
  • Period lock after resolution

2 · Timeline & gates — dated, w/c anchors

WeekDates 2026ActivitiesGate / review
W0Wed 29–Fri 31 JulReply to James accepting the design+oversight role · book the G0 call · circulate this map + the 3 Jun page—
W1Mon 3–Fri 7 AugG0 call with James (Mon/Tue). Field-cut workshop: 27-section brief → the 30 person-record fields that matter · Airtable spine schema built · Tim guardrails call (Thu) · volumes captured: candidates/yr, live principals, invoices/moG0 · scope decision
Fri 7 Aug: spine schema signed
W2Mon 10–Fri 14 AugData population sprint (assisted): every live principal + trailing-12-month candidates into the spine · dedupe pass · commercial fields restricted-access set upG1 · spine live
Fri 14 Aug
W3–W6Mon 17 Aug–Fri 11 SepAssisted operations begin: Workflow A on one live vacancy · Workflow B huddle rhythm starts (all Core principals scheduled) · first month-end reconciliation Mon 31 Aug (Workflow C) · metrics ledger runs from day oneG2 · first cycle proven
Fri 11 Sep
W7–W8Mon 14–Fri 25 SepVolume evidence in → tool pilots only where a trigger fired (§7) · pilots monthly-cancellable · no annual contractsG3 · buy decisions
Fri 25 Sep
W9–W12Mon 28 Sep–Fri 23 OctSecond measured month · build-candidate log matures (every manual join Tim or Anthony touches twice gets logged) · second month-end reconciliation Wed 30 SepWeekly ops reviews
W13Mon 26–Fri 30 OctQuarter review with James. Backlog scored: used-weekly joins qualify · Tim estimates against the proven backlog only · pre-mortem each itemG4 · build gate
w/c 26 Oct
W14+Mon 2 Nov →Tim builds the join (thin Phase-1 scope) · assisted model keeps running — the build replaces steps one at a time, never big-bangMonthly James review

3 · Gate register

GateOwnerThe choiceEntry criteriaExit criteria
G0
w/c 3 Aug
JamesInternal tool · KubiqAI product · both (staged)Volumes known (candidates/yr, principals, invoices/mo) · budget envelope named · Deidre-roadmap contradiction answeredOne-line scope decision minuted · success metric with a number attached
G1
14 Aug
Josh (data) / Anthony (schema)Is the spine trustworthy enough to operate from?30-field schema agreed · restricted fields access-controlled100% live principals + 12-mo candidates loaded · ≥95% completeness on core fields · zero known duplicates
G2
11 Sep
AnthonyDoes assisted mode actually work here?≥1 vacancy run end-to-end · ≥6 huddles held · 1 month-end reconciledCycle time ≤10 working days · AI-draft acceptance ≥70% · every reconciliation exception named + resolved
G3
25 Sep
Anthony + FinanceBuy, defer, or stay-assisted — per category4+ weeks of measured volumesEach trigger table row decided with the number that decided it · pilots monthly-cancellable only
G4
w/c 26 Oct
James (money) / Anthony (scope) / Tim (estimate)What gets built at allQuarter of metrics · build-candidate log · Tim's per-item estimatesBacklog = only joins used ≥weekly in assisted mode · each item pre-mortemed · budget ≤ the number G0 set

4 · Workflow A — assisted recruitment cycle target ≤10 working days brief→decision

5 · Workflow B — engagement rhythm every Core principal, every 4–6 weeks

6 · Workflow C — time → invoice reconciliation weekly rhythm + month-end close

7 · Buy triggers — decided by numbers, not enthusiasm decided at G3 · 25 Sep

CategoryTrigger (measured in W3–W8)If fired → pilotIf not firedIndicative cost
ATS-lite>20 active candidates/month or >2 concurrent vacanciesTeamtailor / Recruit CRM tier, monthly planStay assisted on the spine~£50–150/mo total
PSA (time + capacity)>10 concurrent engagements or >30 timesheets/monthProductive / Scoro (3 Jun shortlist stands)Sheet + AI validation continues~£10–50/user/mo
AP three-way matching>25 supplier invoices/monthRamp / Precoro tierAI rules-sheet check continues (minutes/month at current volume)~£3/invoice
E-sign / LoE repositoryImmediately useful — low costPandaDoc or existing e-sign + versioned folder—~£20–40/mo
Rule from the 3 Jun page, still binding: a £30/head tool is cancellable next month; a build never is. Nothing here gets an annual contract before G4.

8 · Build gate — what Tim actually builds G4 · w/c 26 Oct

A join qualifies for the build backlog only if all four are true, evidenced from the assisted quarter:

Expected backlog shape (prediction to test, not a commitment): the person-record join across recruitment→delivery→finance · permission-aware RAG search over the E5 corpus · the reconciliation join (invoice↔LoE↔time) if invoice volume grows · E5's assessment methodology encoded as configurable workflow. Explicitly not: portals, dashboards, comms modules, workflow engines — configuration or commodity, all of it.

Architecture guardrails for the W1 Tim call — agree these before any estimate exists: (1) spine data is exportable, no lock-in; (2) build extends the assisted stack, doesn't replace it big-bang; (3) modular monolith per the brief §19, Postgres+pgvector fine; (4) watch the Salesforce instinct — Tim is Salesforce-certified (Cloud Developer) and the Kaplan job is Salesforce-shaped; a Salesforce-platform PeopleOS is a licence + consultant annuity, and it must clear the same G4 criteria as any other route, not arrive as a default.

9 · Metrics ledger — what the gates read

MetricFeedsTarget
Recruitment cycle time (brief → categorisation)G2≤10 working days
AI assessment-draft acceptance rate (accepted/edited vs rejected)G2, G4≥70%
Spine completeness — core fields, live principalsG1, weekly≥95%
Huddles on time (≤6 weeks since last contact)weekly ops≥90%
Timesheets in by Fridayweekly ops100% (chase list otherwise)
Invoice exceptions / month + days-to-resolveG3, month-endevery exception named; resolve ≤5 days
Measured volumes: candidates/mo, engagements, invoices/moG3 triggers— (they decide the buys)
Build-candidate log: joins touched ≥2×, with tallyG4—

10 · Review cadence

ReviewWhenWhoStanding agenda
Ops reviewFri 30 min, from 21 AugAnthony, Josh (+Tim optional)Metrics ledger · overdue huddles · exceptions · build-candidate log additions
Month reviewLast Fri: 28 Aug, 25 Sep, 30 Oct+ JamesVolumes vs triggers · gate readiness · budget burn
Gate reviewsG0–G4 per register aboveNamed ownersEntry/exit criteria only — no gate passes on vibes
Quarter build gatew/c 26 OctJames, Anthony, TimBacklog scoring · estimates · pre-mortems · go/no-go per item

The platform the brief describes gets built here too — but each part earns its build by first running as a discipline, assisted. What never earns it, never gets built. That's the whole model.